Cooler CPI and PPI boost gold and ease rate hike bets, but the Fed needs more from core ahead of September – Experts|Arizona Gold and Silver Intersects 21.79 Metres grading 4.10 g/t Gold at Philadelphia|Daily Newsletter|Phenom Reports Commercialization Progress at MK Plus's New Swedish Base|LBMA snapshot survey predicts gold price average near $4,500/oz by year-end|Silver North Continues Haldane Drilling and Commences Veronica Exploration, Yukon|In-line CPI clears the path to $4,600|UBS sees gold price challenging $5,000/oz in H1 2027 on lower real rates, softer USD and strong sovereign demand|Coinbase launches GOLD-PERP and SILVER-PERP futures offering 24/7/365 metals trading and price discovery with 25x leverage|Arizona Gold & Silver Reports Multiple High-Grade Intercepts Including 3.35m of 15.07 gpt Gold and 19.6 gpt Silver – Expands High-Grade Philadelphia Zone|Cooler CPI and PPI boost gold and ease rate hike bets, but the Fed needs more from core ahead of September – Experts|Arizona Gold and Silver Intersects 21.79 Metres grading 4.10 g/t Gold at Philadelphia|Daily Newsletter|Phenom Reports Commercialization Progress at MK Plus's New Swedish Base|LBMA snapshot survey predicts gold price average near $4,500/oz by year-end|Silver North Continues Haldane Drilling and Commences Veronica Exploration, Yukon|In-line CPI clears the path to $4,600|UBS sees gold price challenging $5,000/oz in H1 2027 on lower real rates, softer USD and strong sovereign demand|Coinbase launches GOLD-PERP and SILVER-PERP futures offering 24/7/365 metals trading and price discovery with 25x leverage|Arizona Gold & Silver Reports Multiple High-Grade Intercepts Including 3.35m of 15.07 gpt Gold and 19.6 gpt Silver – Expands High-Grade Philadelphia Zone|
Back to News
Latest News

Azteca processing plant refurbishment reaches 77% completion – Cadence

Azteca processing plant refurbishment reaches 77% completion – Cadence
28 July 20265 Mins read

Refurbishment of the Azteca processing plant at London-listed Cadence Minerals' Amapá iron-ore project, in Brazil, has progressed to 77% completion and 43 of the 64 identified work packages now complete.

The company reports that completion of the principal mechanical workstreams has progressively shifted the execution focus to electrical installation, integrated commissioning and operating licence readiness. The feed hopper, transfer conveyor and process tank installation have been completed, while screen refurbishment is substantially complete.

Cadence says management's immediate focus is completing the remaining electrical installations, integrated plant commissioning and completion of the operating licence workstreams.

Subject to successful commissioning and receipt of the operating licence, the company continues to target operational readiness by the end of August.

The Amapá project is an integrated operation comprising mining, rail, port and beneficiation infrastructure. As part of a staged redevelopment strategy for the project, Azteca is planned to be recommissioned as the initial production facility, targeting about 380000 t/y of about 65% iron concentrate from existing tailings. 

Our Trusted Brands

Arras Minerals
Afrikor
Arizona Gold & Silver
Astra Exploration
Aurion Resources
Bluenergies
Bactech
Digipower X
Gold Hunter Resources
Golkor
Guanajuato
Harfang
He Capital
Kodiak Copper
Leviathan
Loyalist
Mining Investment Event
Noble Plains
Pan Global
Phenom Resources
Power Metallic
SilverWolf
Spacekor
US Gold
USDC
Vivio Power
West Red Lake
Arras Minerals
Afrikor
Arizona Gold & Silver
Astra Exploration
Aurion Resources
Bluenergies
Bactech
Digipower X
Gold Hunter Resources
Golkor
Guanajuato
Harfang
He Capital
Kodiak Copper
Leviathan
Loyalist
Mining Investment Event
Noble Plains
Pan Global
Phenom Resources
Power Metallic
SilverWolf
Spacekor
US Gold
USDC
Vivio Power
West Red Lake

News & Updates

Subscribe to Our Latest News & Updates