▶US dollar up 2% over last 7 sessions, gold down by 10% in the same period|▶Gold prices remain under pressure as Fed minutes show central bank committed to cooling inflation|▶India’s gold demand boosted by lower prices in October, with jewelry, ETFs, and imports strong – WGC’s Chacko|▶Sirios Continues to Expand Gold Mineralization at Cheechoo with an Intercept of 1.09 gt Au over 70.5 m|▶Daily Newsletter|▶As silver underperforms gold, has its bubble popped?|▶Gold price follows the dollar in the short-term, but real yields over the long haul – Heraeus|▶Spot gold slides to $3,756oz as U.S. pending home sales drop 4.7% in October|▶BHP, Rio Tinto executives to meet China leaders as iron-ore pressure builds|▶Brazil contests EU review of Anglo American's nickel mine sale to China's MMG|▶US dollar up 2% over last 7 sessions, gold down by 10% in the same period|▶Gold prices remain under pressure as Fed minutes show central bank committed to cooling inflation|▶India’s gold demand boosted by lower prices in October, with jewelry, ETFs, and imports strong – WGC’s Chacko|▶Sirios Continues to Expand Gold Mineralization at Cheechoo with an Intercept of 1.09 gt Au over 70.5 m|▶Daily Newsletter|▶As silver underperforms gold, has its bubble popped?|▶Gold price follows the dollar in the short-term, but real yields over the long haul – Heraeus|▶Spot gold slides to $3,756oz as U.S. pending home sales drop 4.7% in October|▶BHP, Rio Tinto executives to meet China leaders as iron-ore pressure builds|▶Brazil contests EU review of Anglo American's nickel mine sale to China's MMG|
Back to News
Copper News

Generation Mining starts early works on Marathon palladium, copper project build

Generation Mining starts early works on Marathon palladium, copper project build
02 October 20265 Mins read

TSX-listed Generation Mining has started with construction of the Marathon copper/palladium project, in Ontario.

The company has made initial payments of $30-million to secure critical equipment to site, as part of a broader $150-million 'critical purchase' plan. Some of these orders include crushing infrastructure, grinding and regrind mills, hydrocyclones, flotation equipment, thickeners and cranes.

Subsequent payments will be tied to agreed engineering, fabrication and delivery milestones.

The early works construction programme will run through the fourth quarter and into 2027, and includes upgrades to site access roads, clearing of the plant side, construction of early water management structures, expansion of the camp to meet construction and permanent camp requirements, establishment of a temporary fuel farm and site offices, initial bulk earthworks and aggregate production, and installation of temporary power.

Over the anticipated 13-year mine life of the Marathon project, it will produce about 2.1-million pounds of palladium, 532-million pounds of copper, 488000 oz of platinum, 160000 oz of gold and 3.05-million ounces of silver. 

Our Trusted Brands

Arras Minerals
Afrikor
Arizona Gold & Silver
Astra Exploration
Aurion Resources
Bluenergies
Bactech
Digipower X
Gold Hunter Resources
Golkor
Guanajuato
Harfang
He Capital
Kodiak Copper
Leviathan
Loyalist
Mining Investment Event
Noble Plains
Pan Global
Power Metallic
SilverWolf
Spacekor
US Gold
USDC
Vivio Power
West Red Lake
Arras Minerals
Afrikor
Arizona Gold & Silver
Astra Exploration
Aurion Resources
Bluenergies
Bactech
Digipower X
Gold Hunter Resources
Golkor
Guanajuato
Harfang
He Capital
Kodiak Copper
Leviathan
Loyalist
Mining Investment Event
Noble Plains
Pan Global
Power Metallic
SilverWolf
Spacekor
US Gold
USDC
Vivio Power
West Red Lake

News & Updates

Subscribe to Our Latest News & Updates