▶Daily Newsletter|▶Arrow Minerals targets 400% landholding expansion in iron-ore-rich Pilbara|▶Copper Mark transitions to Veramark Assurance|▶BHP sues union at Spence copper mine over 'illegal' stoppages|▶Canada's Meta Critical Minerals secures military expert Melkon as strategic adviser|▶Cedro garners enviro approval for Brazil's newest iron-ore export terminal|▶World Bank's Banga sets goal of quintupling critical minerals financing in five years|▶Dryden Gold and Eagle Lake First Nation Sign Early Exploration Agreement|▶Coinbase launches GOLD-PERP and SILVER-PERP futures offering 24/7/365 metals trading and price discovery with 25x leverage|▶Arizona Gold & Silver Reports Multiple High-Grade Intercepts Including 3.35m of 15.07 gpt Gold and 19.6 gpt Silver – Expands High-Grade Philadelphia Zone|▶Daily Newsletter|▶Arrow Minerals targets 400% landholding expansion in iron-ore-rich Pilbara|▶Copper Mark transitions to Veramark Assurance|▶BHP sues union at Spence copper mine over 'illegal' stoppages|▶Canada's Meta Critical Minerals secures military expert Melkon as strategic adviser|▶Cedro garners enviro approval for Brazil's newest iron-ore export terminal|▶World Bank's Banga sets goal of quintupling critical minerals financing in five years|▶Dryden Gold and Eagle Lake First Nation Sign Early Exploration Agreement|▶Coinbase launches GOLD-PERP and SILVER-PERP futures offering 24/7/365 metals trading and price discovery with 25x leverage|▶Arizona Gold & Silver Reports Multiple High-Grade Intercepts Including 3.35m of 15.07 gpt Gold and 19.6 gpt Silver – Expands High-Grade Philadelphia Zone|
Back to News
Latest News

Lotus ramps up Kayelekera uranium production, starts acid plant commissioning

Lotus ramps up Kayelekera uranium production, starts acid plant commissioning
10 March 20265 Mins read

Uranium developer Lotus Resources says production ramp-up at the Kayelekera uranium mine in Malawi is progressing, with the operation on track to reach nameplate output in the second quarter of 2026.

The company reported on Tuesday that the processing plant operated at about 80% utilisation during the second half of February, with milling rates reaching roughly 65% of steady-state levels.


Lotus said existing acid inventories and an ongoing delivery schedule would support the ramp-up to full production during the quarter.

Meanwhile, cold commissioning of the mine’s on-site acid plant has begun, with hot commissioning scheduled for April.


The company is also continuing work with converters to complete final product acceptance ahead of uranium deliveries.

MD Greg Bittar said in a statement that operational performance had improved steadily in recent weeks.

The company noted that once final product acceptance is achieved with one converter, it will be able to swap product between converters, providing greater flexibility across supply contracts and future uranium sales.

Our Trusted Brands

Arras Minerals
Afrikor
Arizona Gold & Silver
Astra Exploration
Aurion Resources
Bluenergies
Bactech
Digipower X
Gold Hunter Resources
Golkor
Guanajuato
Harfang
He Capital
Kodiak Copper
Leviathan
Loyalist
Mining Investment Event
Noble Plains
Pan Global
Power Metallic
SilverWolf
Spacekor
US Gold
USDC
Vivio Power
West Red Lake
Arras Minerals
Afrikor
Arizona Gold & Silver
Astra Exploration
Aurion Resources
Bluenergies
Bactech
Digipower X
Gold Hunter Resources
Golkor
Guanajuato
Harfang
He Capital
Kodiak Copper
Leviathan
Loyalist
Mining Investment Event
Noble Plains
Pan Global
Power Metallic
SilverWolf
Spacekor
US Gold
USDC
Vivio Power
West Red Lake

News & Updates

Subscribe to Our Latest News & Updates