▶Daily Newsletter|▶Arrow Minerals targets 400% landholding expansion in iron-ore-rich Pilbara|▶Copper Mark transitions to Veramark Assurance|▶BHP sues union at Spence copper mine over 'illegal' stoppages|▶Canada's Meta Critical Minerals secures military expert Melkon as strategic adviser|▶Cedro garners enviro approval for Brazil's newest iron-ore export terminal|▶World Bank's Banga sets goal of quintupling critical minerals financing in five years|▶Dryden Gold and Eagle Lake First Nation Sign Early Exploration Agreement|▶Coinbase launches GOLD-PERP and SILVER-PERP futures offering 24/7/365 metals trading and price discovery with 25x leverage|▶Arizona Gold & Silver Reports Multiple High-Grade Intercepts Including 3.35m of 15.07 gpt Gold and 19.6 gpt Silver – Expands High-Grade Philadelphia Zone|▶Daily Newsletter|▶Arrow Minerals targets 400% landholding expansion in iron-ore-rich Pilbara|▶Copper Mark transitions to Veramark Assurance|▶BHP sues union at Spence copper mine over 'illegal' stoppages|▶Canada's Meta Critical Minerals secures military expert Melkon as strategic adviser|▶Cedro garners enviro approval for Brazil's newest iron-ore export terminal|▶World Bank's Banga sets goal of quintupling critical minerals financing in five years|▶Dryden Gold and Eagle Lake First Nation Sign Early Exploration Agreement|▶Coinbase launches GOLD-PERP and SILVER-PERP futures offering 24/7/365 metals trading and price discovery with 25x leverage|▶Arizona Gold & Silver Reports Multiple High-Grade Intercepts Including 3.35m of 15.07 gpt Gold and 19.6 gpt Silver – Expands High-Grade Philadelphia Zone|
Back to News
Latest News

Nyanzaga gold project advances toward first gold production in 2027

Nyanzaga gold project advances toward first gold production in 2027
04 February 20265 Mins read

Construction at Perseus Mining’s Nyanzaga gold project, in Tanzania, is progressing steadily, with key milestones achieved across operational, mining, and community programmes, the company reported in its first 2026 project update on February 4. The project remains on track to produce its first gold in the first quarter of 2027.

As of mid-January, the operation has recorded nearly four-million workhours with 358 days without a lost-time injury. The first concrete lift on the ball and sag mill has been completed, while installation of the carbon-in-leach tanks continues as planned. Four tanks have reached top strake jacking, and three tanks are progressing with floor plate installation.


Construction of the permanent camp is also advancing, with completion scheduled for mid-2026, providing essential facilities for the workforce. Initial mining preparation has also commenced on the ramp to the top of the Tusker Hill deposit, signalling the start of early extraction activities.

Meanwhile, community and resettlement programmes have moved into their final stages. The resettlement housing programme is completing the last homes, and infrastructure work has begun at schools, a local clinic, and a church. These initiatives are part of the project’s efforts to support local communities alongside mining operations. 

Our Trusted Brands

Arras Minerals
Afrikor
Arizona Gold & Silver
Astra Exploration
Aurion Resources
Bluenergies
Bactech
Digipower X
Gold Hunter Resources
Golkor
Guanajuato
Harfang
He Capital
Kodiak Copper
Leviathan
Loyalist
Mining Investment Event
Noble Plains
Pan Global
Power Metallic
SilverWolf
Spacekor
US Gold
USDC
Vivio Power
West Red Lake
Arras Minerals
Afrikor
Arizona Gold & Silver
Astra Exploration
Aurion Resources
Bluenergies
Bactech
Digipower X
Gold Hunter Resources
Golkor
Guanajuato
Harfang
He Capital
Kodiak Copper
Leviathan
Loyalist
Mining Investment Event
Noble Plains
Pan Global
Power Metallic
SilverWolf
Spacekor
US Gold
USDC
Vivio Power
West Red Lake

News & Updates

Subscribe to Our Latest News & Updates